Programme: 6 Weeks

Completion: Sept 2022 

Description: Education Interior Fit-Out

Size: 11,000 sqft

PROJECT

King Edward VI College – Creative Arts & Digital Media Centre, Nuneaton

Perched on the first floor of the Ropewalk Shopping Centre, this 1000 m² fit-out transformed redundant office space into a fully-functioning education hub for King Edward VI College—complete with music studios, photography suites and an e-sports arena—just in time for the September term. The location never closed to the public, so every activity had to dovetail with centre operations, fire routes and noise restrictions.

Facing a ten-week window from concept sign-off to handover, our team fast-tracked design, procurement and build in parallel. Early contractor-involvement workshops locked down M&E coordination and acoustic performance targets within the first week, allowing us to release long-lead items immediately.

Key works

  • Full strip-out & enabling of legacy services and CAT A finishes

  • HVAC overhaul: new VRF systems, heat-recovery ventilation and roof penetrations coordinated with centre management

  • Specialist acoustic glazing & partitions delivering STC 55 between music studios and teaching areas

  • BM Trada fire-rated door sets, integrated access-control & new data backbone for 10 Gbps connectivity

  • Relocation of a sensitive sound-booth from the main college campus, completed out-of-hours to avoid term-time disruption

  • Finishes: durable vinyl & carpet-tile flooring, LED lighting to 500 lux, and a bold decorative scheme aligned with the college’s brand

Outcome

We achieved sectional completion two days ahead of programme, enabling staff to commission equipment and rehearse before students arrived. Independent acoustic tests surpassed the brief by 3 dB, and post-occupancy surveys report 96 % user satisfaction. Impressed by the pace and quality of delivery, the client has already engaged us on a follow-on project for its main campus—proof that Thornwood can design, build and deliver under pressure, anywhere in the UK.

​

​

From Start to finish, the Thornwood team was on site, making sure everything happened when it needed to, and crucially, it was on track to meet that tight end-of-August deadline. They did this with flying colours, and that was an exemplary piece of work, which meant that we will continue to work with them in the future. 

​

We're already exploring with them the opportunity to convert the other floors of the building to make this a centrepiece educational space at the heart of Nuneaton for Students and the community to really benefit from and gain from. â€‹â€‹

​

This has become our show home, the standard and model by which we seek to do everything else now. Because of Thornwood, we were able to set the highest standards possible. 

​

Stuart Noss - Principal

Enquire Now
bottom of page